Right Answer: Nominal mix refers to a fixed proportion of ingredients (cement, sand, aggregate) used in concrete, typically based on standard ratios (like 1:2:4). Design mix, on the other hand, is a tailored mix designed based on specific project requirements, considering factors like strength, durability, and workability, and is determined through testing and calculations.
Right Answer: The documents submitted by the contractor initially entering a new site for a client in a process plant include:
1. Project Execution Plan (PEP)
2. Health, Safety, and Environmental (HSE) Plan
3. Quality Assurance/Quality Control (QA/QC) Plan
4. Construction Schedule
5. Method Statements
6. Risk Assessment and Management Plan
7. Material Submittals
8. Personnel Qualifications and Certifications
9. Site Layout Plan
10. Insurance Certificates and Bonds