Ques:- Why do we have two types of scheduling options in Primavera – Retained logic and progress override? What is the difference between the two and when is either one selected?
Asked In :-
FUTURISM TECHNOLOGIES PVT, Techversant Infotech, Techathalon Software Solutions, INAPP INFORMATION TECHNOLOGIES INDIA PVT, 63 moons technologies, Talent Smart Soft Solutions (OPC), MaxVal-IP Services, PRORIGO SOFTWARE PVT, Kalki Communication Technologies, PMaps Assessment,
Right Answer:
In Primavera, we have two types of scheduling options: Retained Logic and Progress Override.
- **Retained Logic** maintains the original relationships and dependencies between tasks, ensuring that the schedule reflects the planned sequence of work. It is selected when you want to keep the integrity of the project plan intact.
- **Progress Override** allows for adjustments to the schedule based on actual progress, which can change the relationships between tasks. It is selected when you need to reflect real-time updates and changes in task completion that may affect the overall schedule.
Use Retained Logic for accurate planning and Progress Override for flexibility in managing ongoing project changes.
In Primavera, we have two types of scheduling options: Retained Logic and Progress Override.
- **Retained Logic** maintains the original relationships and dependencies between tasks, ensuring that the schedule reflects the planned sequence of work. It is selected when you want to keep the integrity of the project plan intact.
- **Progress Override** allows for adjustments to the schedule based on actual progress, which can change the relationships between tasks. It is selected when you need to reflect real-time updates and changes in task completion that may affect the overall schedule.
Use Retained Logic for accurate planning and Progress Override for flexibility in managing ongoing project changes.