Find Interview Questions for Top Companies
Jack henry & associates Interview Questions and Answers
Ques:- How do you manage working on projects with new technology or tools you’re not familiar with
Right Answer:
I approach new technologies by first researching and understanding the basics through documentation and tutorials. I then practice using the tools in small projects or exercises to gain hands-on experience. Additionally, I seek help from colleagues or online communities when needed, and I stay adaptable by being open to learning and adjusting my approach as I gain more knowledge.
Ques:- What is Bank Reconcilation Statement?
Right Answer:
A Bank Reconciliation Statement is a document that compares and reconciles the bank balance shown in a company's accounting records with the balance shown on the bank statement. It identifies any differences between the two records, such as outstanding checks or deposits in transit, to ensure accuracy in financial reporting.
Ques:- Is there a difference between accounting for conversion of bonds and accounting for the conversion of preferred stock?
Right Answer:
Yes, there is a difference. When bonds are converted into stock, the carrying amount of the bonds is removed from the books, and the stock is recorded at fair value or par value, depending on the accounting policy. In contrast, when preferred stock is converted into common stock, the preferred stock is removed at its carrying amount, and the common stock is recorded at par value, with any excess typically going to additional paid-in capital.
Ques:- What is tax slab for the salaried person?
Right Answer:
The tax slab for salaried individuals in India for the financial year 2023-24 is as follows:

1. Income up to ₹2.5 lakh: Nil
2. Income from ₹2,50,001 to ₹5,00,000: 5%
3. Income from ₹5,00,001 to ₹10,00,000: 20%
4. Income above ₹10,00,000: 30%

Additionally, there is a rebate under Section 87A for individuals with income up to ₹5 lakh.
Ques:- How to depict dependency in Ms Project?
Right Answer:
To depict dependency in MS Project, you can link tasks by selecting the tasks you want to connect, then clicking on the "Link Tasks" button in the toolbar or using the shortcut Ctrl + F2. This creates a finish-to-start dependency by default. You can also adjust the type of dependency (finish-to-start, start-to-start, finish-to-finish, or start-to-finish) by double-clicking on the task and modifying the "Predecessors" tab.
Ques:- What are the fields used for Project Planning in Ms Project?
Right Answer:
The fields used for Project Planning in MS Project include:

1. Task Name
2. Duration
3. Start Date
4. Finish Date
5. Predecessors
6. Resources
7. Percent Complete
8. Work
9. Cost
10. Milestones
Ques:- Given Data for doing different formats like pivot, and matching the data for another data
Right Answer:
To analyze data for different formats like pivot tables and matching datasets, you should:

1. **Identify Key Variables**: Determine the key fields that will be used for matching and pivoting.
2. **Clean the Data**: Ensure that the data is free from duplicates, errors, and inconsistencies.
3. **Use Pivot Tables**: Create pivot tables to summarize and analyze the data by aggregating values based on categories.
4. **Match Data**: Use functions like VLOOKUP or JOIN operations in SQL to match data from different sources based on the identified key variables.
5. **Validate Results**: Check the accuracy of the matched data and the pivot table outputs to ensure they meet business requirements.
AmbitionBox Logo

What makes Takluu valuable for interview preparation?

1 Lakh+
Companies
6 Lakh+
Interview Questions
50K+
Job Profiles
20K+
Users